Sunrise Powerlink Alpine Construction Summary

April 16, 2012

  • All transmission line construction activity on Alpine Boulevard has been completed. Construction activities for the County of San Diego's Streetscape Improvement Plan and 20A utility undergrounding effort are continuing.

  • On March 26, the Alpine Community Planning Board voted to support the County of San Diego's Phase II Streetscape plans. This work includes expediting the County's storm drain design and placing 17 inch storm drains along Alpine Boulevard.
  • Per SDG&E's original agreement with the County of San Diego and its commitment to the community, SDG&E will pave with rubberized asphalt west of Tavern Road and East of South Grade Road as scheduled within the next several months. However, at the County of San Diego's request, rubberized asphalt paving in the downtown area will be delayed until the County completes its storm drain work.
  • As of April 16, SDG&E has completed all 40 vaults, transmission line trenching, and cable installation and splicing on Alpine Boulevard. Overall construction on the Alpine underground segment is more than 95 percent complete.

Outlook for week of April 16-21:

  • Working on San Diego County's streetscape improvements west of South Grade Road and east and west of West Victoria, Monday-Friday. Working on the 20A utility undergrounding effort east and west of South Grade Road, Monday-Friday.

Outlook for week of April 23-28:

  • Working on San Diego County's streetscape improvements west of South Grade Road and east and west of West Victoria, Monday-Friday. Working on the 20A utility undergrounding effort east and west of South Grade Road, Monday-Friday.

All construction activities listed above are taking place along Alpine Boulevard. Cross streets are provided as a reference only. Construction is taking place from 7 AM to 5 PM.

The information provided above is a general overview of potential construction activities for the weeks of April 16-21 and April 23-28. Business requests, weather conditions and other considerations will be taken into account when determining daily work assignments. Construction schedules are subject to change without notice.